Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
A . Requirements documentation
B . Requirements traceability matrix
C . Project management plan updates
D . Project documents updates
Answer: B