Which COBIT domain of management objectives incorporates managed business process controls?
Which COBIT domain of management objectives incorporates managed business process controls?
A . Build, Acquire and Implement (BAI)
B . Align, Plan and Organize (APO)
C . Deliver, Service and Support (DSS)
Answer: C
Explanation:
Reference: https://graser.co.at/en/cobit-5-understand-the-framework/