Which Cluster Deployment document must be completed with the customer?

A consultant is planning an installation and needs to collect configuration items to be used during the install. The data needed from the customer are IP addresses, Gateway, DNS servers, and NTP Servers.

Which Cluster Deployment document must be completed with the customer?
A . Project Plan
B . Operations Guide
C . Questionnaire
D . Technical Checklist

Answer: D