Which ceremony should be used in developing this register?
An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.
Which ceremony should be used in developing this register?
A . Sprint plans
B . Retrospective results
C . Sprint report
D . Project status report
Answer: A