Which Calculation Method can calculate a benefit structure on a total quantity of 150 units, where the first 100 units earn $0 per unit and the next 50 units earn $10 per unit?

Which Calculation Method can calculate a benefit structure on a total quantity of 150 units, where the first 100 units earn $0 per unit and the next 50 units earn $10 per unit?
A . Specified
B . Elapsed
C . Stepped
D . Aggregate

Answer: C