Topic 4, Misc. Questions
You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.
Subproduction orders for the subcomponent must be created when estimating production orders.
You need to configure the BOM line to generate subproduction orders.
Which BOM line type should you use?
A . Phantom
B . Vendor
C . Item
D . Pegged supply
Answer: D
Explanation:
References: https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/bill-of-material-bom