Which assignment do you make to create external process steps in process oriented storage control? Please choose the correct answer.

Which assignment do you make to create external process steps in process oriented storage control? Please choose the correct answer.
A . external process step to a work Centre
B . external process step to and SAP internal process step
C . external process step to a packaging specification
D . external process step to a storage type

Answer: B