Which aspect of project performance must be managed to ensure the project’s products are fit for purpose?
Which aspect of project performance must be managed to ensure the project’s products are fit for purpose?
A . Benefits
B . Quality
C . Risk
D . Scope
Answer: B
Explanation:
Quality is the aspect of project performance that must be managed to ensure the project’s products are fit for purpose. PRINCE2® emphasizes that quality management is essential to ensure that the project outputs meet the necessary requirements and standards to achieve the desired outcomes.
Reference: PRINCE2® Foundation official documentation and study materials.
These responses are based on the latest materials and guidelines from the PRINCE2® Foundation, ensuring accurate and up-to-date answers as per your request.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund