A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.
Which approach should the project manager use in this situation?
A . Hybrid approach
B. Predictive approach
C. Kanban approach
D. Agile approach
Answer: A