Ann app builder has been to display an overdue date that is two months after a tasks due date.

Which approach should the app builder take?
A . Use process builder and set overdue date equal to DueDate + ((365/12)*2)
B. Create a formula field using DueDate + 60
C. Use process builder and set overdue Date equal to DueDate + 60
D. Create a formula field using the ADDMONTHS () function

Answer: D