A company is changing its case management system to Salesforce. All active accounts, contacts, and closed cases for the past 5 years must be migrated to Salesforce for go-live.
Which approach should be used for the data migration?
A . Prepare, Plan, Test, Execute, Validate
B . Plan, Prepare, Test, Execute, Validate
C . Prepare, Plan, Validate, Execute, Test
D . Plan, Prepare, Validate, Execute, Test
Answer: D