Which approach should a Consultant recommend to realign available resources with open work?
An extreme weather situation impacted both the volume of open work and the number of available resources at Universal Containers.
Which approach should a Consultant recommend to realign available resources with open work?
A . Resource Schedule Optimization
B. Emergency scheduling
C. Global optimization
D. Customer First scheduling
Answer: B