Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?

Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?
A . Analyse stakeholders
B . Sum ma rise risks
C . Carry out a health check
D . Conduct a visioning workshop

Answer: D