Which activity helps the project team to add the user stories to the product backlog? Please choose the answer.

Which activity helps the project team to add the user stories to the product backlog? Please choose the answer.
A . Planning the User Acceptance Test
B . Conducting the Solution Validation
C . Assessing Project Risks
D . Preparing a Project Schedule

Answer: B