Which activity helps the project team identify and add user stories to the backlog?
A . Planning the User Acceptance Testing
B . Conducting the fit-to-standard workshop
C . Preparing a project schedule and budget
D . Assessing project risks and issues
Answer: B
Explanation:
B is correct because conducting the fit-to-standard workshop helps the project team identify and add user stories to the backlog. The fit-to-standard workshop is a process of analyzing the gaps between the customer’s business requirements and the standard SAP functionality, and documenting the user stories that describe the desired outcomes and acceptance criteria.
Verified Reference: SAP Activate Project Management Certification Guide, page 122