Site icon Exam4Training

Which activity helps the Project Team add User Stories to the Product Backlog?

Which activity helps the Project Team add User Stories to the Product Backlog?
A . Assessing project risks
B . Preparing a project schedule
C . Conducting the Solution Validation workshop
D . Planning the User Acceptance Test

Answer: C

Exit mobile version