Which activities will a Product Owner likely engage in during a Sprint? (choose the best three answers)

Which activities will a Product Owner likely engage in during a Sprint? (choose the best three answers)
A . Run the Daily Scrum
B. Reorder items in the Product Backlog
C. Update the Sprint burndown chart.
D. Answer questions from the Developers about items in the current Sprint.
E. Gather information and opinions from Stakeholders
F. Prioritize the Developer’s tasks.

Answer: B,D,E

Explanation:

A Product Owner orders the work for a complex problem into a Product Backlog.

Product Owner is accountable for maximizing the value of the product The Product Owner may represent the needs of many stakeholders in the Product Backlog.

The Product Owner is also accountable for effective Product Backlog management, which includes:

● Developing and explicitly communicating the Product Goal;

● Creating and clearly communicating Product Backlog items;

● Ordering Product Backlog items; and,

● Ensuring that the Product Backlog is transparent, visible and understood. Incorrect: The Sprint burndown would be update by Developers.

Incorrect: Product owner do not priorize Developer’s tasks, they organize their tasks.