Which activities must you complete before you can activate real-time replication? Note: There are 2 correct answers to this question.
Which activities must you complete before you can activate real-time replication? Note: There are 2 correct answers to this question.
A . Configure the Application Interface Framework.
B . Correct all errors associated with the initial load.
C . Configure the VCFIN_SOURCE_SET view in the corresponding source systems.
D . Delete the extract of the initial load data.
Answer: A, C