Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.

Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.
A . Upload customer master data in the Starter system using migration templates.
B . Deactivate scope items that are NOT part of the Statement of Work/Digital Discovery Assessment
C . Evaluate the L2 Business-Driven Configuration Questionnaire responses.
D . Review the integration requirements collected from the Digital Discovery Assessment.

Answer: C, D