Which action will allow you to meet the connectivity requirements?

Refer to the exhibit.

You are required to implement traffic segmentation in the network. See the table for relevant device details:

L2SW4, L2SW5, and L2SW6 are connected to L3SW1 with 802.1Q trunks with VLAN 191 and VLAN 398 allowed on the trunk.

You have the following information from L3SW1:

L3SW1# show run interfaces

interface Vlan1

no ip address

shutdown

!

interface Vlan2

ip address 10.2.2.2 255.255.255.248

!

interface Vlan191

ip address 10.10.27.126 255.255.255.192

!

interface Vlan200

ip address 10.20.20.1 255.255.255.248

!

interface Vlan398

ip address 10.15.153.1 255.255.255.0

L3SW1# show ip route

*** Output Omitted *** 10.0.0.0/8 is variably subnetted, 5 subnets, 3 masks

C 10.2.2.1/29 is directly connected, Vlan2

C 10.10.27.64/26 is directly connected, Vlan191

C 10.15.153.0/24 is directly connected, Vlan398

C 10.20.20.0/29 is directly connected, Vlan200

S 10.200.200.0/24 [1/0] via 10.20.20.2

S* 0.0.0.0/0 [1/0] via 10.2.2.1

You are required to implement a configuration that will meet the following connectivity requirements:

• The Administrator’s Station must have full access to PanelView

• PanelView should have limited access, based on specific TCP ports, to PLC#1 and I/O#1

The Administrator’s Station should have no access to PLC#1 and I/O#1

PLC#1 and I/O#1 should be able to communicate with each other on any port

Which action will allow you to meet the connectivity requirements?
A . Put interface VLAN 191 and interface VLAN 398 into different Virtual Routing and Forwarding (VRF) instances on L3SW1
B . Deploy an inbound ACL on interface VLAN 191 to control the traffic from the Administrator’s Station and PanelView to PLC#1 and I/O#1
C . No change is required, the traffic is already limited appropriately by the VLAN segmentation
D . Implement an ACL on Firewall1 to control the traffic flow between VLAN 191 and VLAN 398

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments