Which action should the stakeholder take to log the risk?

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?
A . Log a risk as part of the project business case and identify it as a "schedule" risk.
B . Log an issue on the project and explain that the completion date is at risk.
C . Create a task in the project and set the Planned Completion Date for 2 weeks.

Answer: A

Explanation:

In Adobe Workfront, risks associated with a project should be logged as part of the project business case. The "Risk" section within the business case allows stakeholders to document any potential threats to the project timeline, scope, or resources. Identifying this risk as a "schedule" risk helps communicate the potential delay to the project stakeholders and allows it to be tracked and mitigated effectively.