Which action should the project manager take as a priority?
A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.
Which action should the project manager take as a priority?
A . Emphasize the use of Kanban methodology.
B . Ensure the project sponsor is aware of the go-to market date
C . Deliver business value as soon as possible
D . Implement a plan-do-check-act (PDCA) cycle
Answer: C