Which action should the administrator perform to ensure replications can occur without waiting for the backups to complete?

A NetBackup primary server has many backups running each night to an MSDP pool that take a long time to complete. While these backups are running, replication jobs are queued.

Which action should the administrator perform to ensure replications can occur without waiting for the backups to complete?
A . increase the "Maximum I/O Streams" for the disk pool
B . increase "Maximum concurrent jobs" for the disk storage unit
C . increase "Priority for secondary operations" in the storage lifecycle policy
D . increase "Maximum concurrent jobs" in the storage server properties

Answer: B