Which action must be taken while replacing the faulty unit?

A network security engineer must replace a faulty Cisco FTD device in a high availability pair.

Which action must be taken while replacing the faulty unit?
A . Shut down the Cisco FMC before powering up the replacement unit.
B . Ensure that the faulty Cisco FTD device remains registered to the Cisco FMC.
C . Unregister the faulty Cisco FTD device from the Cisco FMC
D . Shut down the active Cisco FTD device before powering up the replacement unit.

Answer: C

Latest 300-710 Dumps Valid Version with 153 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments