An engineer must configure a Layer 3 connection to the WAN router. The hosts in production VRF must access WAN subnets. The engineer associates EPGs in the production VRF with the external routed domain.

Which action completes the task?
A . Configure the Export Route Control Subnet scope for the external EPG.
B. Configure the External Subnets for the External EPG scope for the external EPG.
C. Configure the Import Route Control Subnet scope for the external EPG.
D. Configure the Shared Route Control Subnet scope for the external EPG.

Answer: A