Which action completes the task?

An engineer must configure a Layer 3 connection to the WAN router. The hosts in production VRF must access WAN subnets. The engineer associates EPGs in the production VRF with the external routed domain.

Which action completes the task?
A . Configure the Export Route Control Subnet scope for the external EPG.
B. Configure the External Subnets for the External EPG scope for the external EPG.
C. Configure the Import Route Control Subnet scope for the external EPG.
D. Configure the Shared Route Control Subnet scope for the external EPG.

Answer: A

Latest 300-620 Dumps Valid Version with 78 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments