Which 2 statements should be recorded under the Timescale heading?
A . Benefits will be lost if the project is not completed on time.
B . A recruitment campaign to fill the existing staff vacancies will need to take place in the next 12 months.
C . Additional 10% increase in orders in year two.
D . The prepared calendar pack must be delivered by the first week in December.
E . The print company requires a 2 week notification period of the calendar pack delivery.
Answer: CD