Which 2 statements should be recorded under the Timescale heading?
Which 2 statements should be recorded under the Timescale heading?
A . The contract with the selected service provider will be agreed during stage 3.
B . The expected benefits will be calculated over 10 years from completion of the project.
C . If more MFH divisions are added to the scope of the services to be outsourced, the project timescale will be extended and the realization of benefits will be delayed.
D . The expected benefits should start to be realized as soon as the outsourced services become operational at the end of stage 4.
E . The transfer of equipment and staff is estimated to take six weeks.
Answer: AB