Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
A . The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.
B . Enough description of the required refurbishment work should be provided to enable the Architecture Angels’ Finance Director to decide whether the project should proceed.
C . During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
D . The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.
E . The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.

Answer: BC

Explanation:

In applying Agile Project Management to the creation of an Outline Business Case in support of the

Feasibility Assessment, the following two statements are most appropriate:

B. Enough description of the required refurbishment work should be provided to enable the Architecture Angels’ Finance Director to decide whether the project should proceed.

Agile approaches favor providing just enough detail to make informed decisions without going into unnecessary depth at early stages. This allows for flexibility and adaptation as more information becomes available.

C. During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.

Agile methodologies emphasize stakeholder engagement and user involvement early and throughout the project. This ensures that the project delivers value and meets the needs of those it is intended to benefit.