Which 2 alternative actions apply to the proposed supplier assurance for this project?
Which 2 alternative actions apply to the proposed supplier assurance for this project?
A . Retain because he has a professional facilities qualification and so is in a position to specify the needs of his division.
B . Retain because he will be able to advise on many of the products that will enable outsourcing to happen, such as the 10-year outsourcing service contract.
C . Retain because he is well-regarded within the Ministry because of the efficiencies, superb service and savings he has achieved in the Facilities Division.
D . Add ‘Outcome Account Manager’ because he will advise on potential changes and their impact on the integrity of the project’s products.
E . Remove because he is involved with the project and is therefore NOT independent.
Answer: BD