Which 2 alternative actions apply to the proposed Senior User for this project?

Which 2 alternative actions apply to the proposed Senior User for this project?
A . Retain because he provides the outsourcing resources required to support the project.
B . Replace with ‘Director of Research and Development’ because she deals with both the Information Technology and the Facilities Divisions and can make sure her division’s needs are specified.
C . Remove because he has no authority to commit user resources.
D . Add ‘Hardware Manager’ because he provides computer hardware to all business functions and will be impacted by the outcome.
E . Retain because he will be providing support to the Information Technology and Facilities teams during the project.

Answer: BC