Where should the testing requirements have been recorded?
A project manager expected a vendor to complete testing of each component they produced and was surprised to discover that no testing was done. To recover, the project team performs a statistical sampling of the components
Where should the testing requirements have been recorded?
A . Quality management plan
B . Procurement management plan
C . Contract change documentation
D . Requirements management plan
Answer: B