Where should the buyer cancel the job?
A company uses Planning Optimization as a scheduled batch job every Friday. A buyer observes that there are unposted inventory cycle counts left over from a weekend physical inventory count. The buyer decides to cancel the Planning Optimization job, post the cycle counts, and run the job again.
Where should the buyer cancel the job?
A . Recurring integration scheduler (RIS)
B . Batch group
C . Feature management
D . Job history
E . Lifecycle Services (LCS)
Answer: D
Explanation:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/cancel-planning-job