Where can you maintain the planned delivery time used for scheduling in material requirements planning? Note: There are 3 correct Answers to this question.

Where can you maintain the planned delivery time used for scheduling in material requirements planning? Note: There are 3 correct Answers to this question.
A . Purchasing info record
B . Outline agreement
C . Plant parameters
D . Material
E . Supplier

Answer: A, D, E