Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
A . In the project profile
B. In the project version
C. In the project type
D. In the project definition of a standard WBS
E. In the operative WBS element

Answer: A,C,E