Where are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
A . Put them on a separate list on the Scrum board, available for all to see.
B . Add them to the Product Backlog and keep the Product Owner posted on the expected effort.
C . Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
D . Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
E . Add them to the definition of “Done” so the work is taken care of every Sprint.
Answer: B,E
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund