When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
A . Realize phase scope, planning, and budget should be completed and final.
B . Release plan and sprint ceremony guidelines should be finalized.
C . Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
D . User stories on product backlog should be in ready state for the first 2 to 3 sprints.
Answer: C
Explanation:
C is correct because in an Agile approach, the planning is done iteratively and incrementally, so the minimum requirement at the beginning of the Realize phase is to have sprint planning and sprint durations defined for the first 2 to 3 sprints.
Verified Reference: SAP Activate Project Management Certification Guide, page 117