When using the budget check, a parameter is set to either absolute or warning, what effects do these options have?

When using the budget check, a parameter is set to either absolute or warning, what effects do these options have?
A . Warning: preparer’s are only notified when the budget is over its limit
B. Warning: The requester’s manager is added as a watcher when the budget is exceeded
Absolute: The requester’s manager is added as anapprover when the budget is exceeded
C. Warning: preparers are able to submit requisitions that exceed the budget
Absolute: preparer’s are only able to submit requisitions that are within the budget
D. Warning: A budget approver is added only When the budgeting is exceeded Absolute: A budget approver is always added

Answer: C