When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)
A . Cycle Time
B. Work in Progress (WIP)
C. Work Item Age
D. Cumulative Flow Diagram (CFD)
E. Lead Time
F. Throughput
Answer: A,B,C,F
Explanation:
The four basic metrics of flow that Scrum Teams using Kanban need to track are as follows:
Work in Progress (WIP): The number of work items started but not finished.
Cycle Time: The amount of elapsed time between when a work item starts and when a work item finishes.
Work Item Age: The amount of time between when a work item started and the current time. This applies only to items that are still in progress.
Throughput: The number of work items finished per unit of time.