When two Scrum Teams are working on the same product you should normalize their estimations to be able to compare their performance.
When two Scrum Teams are working on the same product you should normalize their estimations to be able to compare their performance.
A . False
B. True
Answer: A
Explanation:
It is never reliable to compare the velocity of two teams.