Exam4Training

When tracking team progress, what can a Kanban board show the team?

When tracking team progress, what can a Kanban board show the team?
A . Where the team has too much work-in-process (WIP)
B. The accumulated value of the team’s work
C. A burndown chart of the work completed in the Iteration

Answer: A

Explanation:

Read more: https://www.scaledagileframework.com/team-kanban/

Latest POPM Dumps Valid Version with 180 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version