When there are multiple Scrum Teams working on the same product, each team should demonstrate its individual Increment in a separate branch of the code.
When there are multiple Scrum Teams working on the same product, each team should demonstrate its individual Increment in a separate branch of the code.
A . False
B. True
Answer: A
Explanation:
If there are multiple Scrum Teams working on the system or product release, the Developers on all the Scrum Teams must mutually define the definition of "Done". Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.
The Developers are required to conform to the Definition of Done. If there are multiple Scrum Teams working together on a product, they must mutually define and comply with the same Definition of Done.