When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner’s Project Requirements (OPR)?

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner’s Project Requirements (OPR)?
A . All applicable codes and standards
B . Interior finishes related to the project
C . All project team members and applicable roles
D . Energy efficiency goals and training requirements

Answer: D

Explanation:

Energy efficiency goals and training requirements are required to be present in the Owner’s Project Requirements (OPR) when applying the Integrative Process to a Building Design and Construction project. According to the LEED v4 BD+C Reference Guide, the OPR is a document that details the ideas, concepts, and criteria that are determined by the owner to be important to the success of the project 1.

The OPR must include, among other things, the following information related to energy efficiency 1:

The owner’s energy performance goals and expectations

The owner’s requirements for energy metering and monitoring

The owner’s requirements for energy modeling and analysis

The owner’s requirements for commissioning and verification

The owner’s requirements for training and documentation

The other options are not required to be present in the OPR, as they are either related to other aspects of the project, such as codes and standards, interior finishes, or project team members, or they are not relevant to the Integrative Process, which focuses on early analysis of energy, water, and site systems 2.

Reference: LEED v4 BD+C Reference Guide, Integrative Process Category, IPc Integrative Process, page 632.