When should the Project Board refer to corporate or programme management for a decision?
A . The stage requires resources
B . It is forecast that project level tolerance will be exceeded
C . The Senior Supplier or Senior User needs to be changed
D . Any request for change needs to be approved
Answer: B
Explanation:
The Project Board should refer to corporate or programme management for decisions when it is forecast that the project level tolerance will be exceeded. This scenario typically triggers an exception process as the predefined tolerances are fundamental limits within which the Project Board allows the Project Manager to manage the project.
Reference: PRINCE2® Foundation official study guide and materials.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund