When should the Product Owner update the project plan? (Choose the best answer)

When should the Product Owner update the project plan? (Choose the best answer)
A . The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
B . The project plan must be updated prior to the Sprint Retrospective.
C . Before the Sprint Planning to know how much work will have to be done in the Sprint.
D . After the Daily Scrum to ensure an accurate daily overview of project progress.

Answer: A

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments