When should the Product Backlog be updated? (Choose the best answer)
A . During the Sprint Retrospective.
B . Before the first Sprint starts.
C . When the Product Owner has time.
D . Before each Sprint Planning to know which items to commit to the upcoming Sprint.
E . As new information and insights emerge.
Answer: E