When should quality planning be performed?
When should quality planning be performed?
A . While developing the project charter
B. In parallel with the other planning processes
C. As part of a detailed risk analysis
D. As a separate step from the other planning processes
Answer: B
Latest CAPM Dumps Valid Version with 1089 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments