When should Node Replication be scheduled to run?
A . when the database backupis running
B . when no restore clients are running
C . when no other Admin processes are running
D . when backup-archive clients are running
Answer: C
Explanation:
Ensure that you are running node replication after client backup.
Complete data deduplication processing before replication processing. Schedule compression after replication.
Figure. Daily schedule when data deduplication and node replication are used
References:https://www.ibm.com/support/knowledgecenter/SSEQVQ_8.1.0/perf/t_srv_sched_deduprep.html
Latest C9060-528 Dumps Valid Version with 128 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund