When should a full risk assessment and authorization be carried out for a standard change?
When should a full risk assessment and authorization be carried out for a standard change?
A . Each time the standard change is implemented
B . When the procedure for the standard change is created
C . At least once a year
D . When an emergency change is requested
Answer: B
Latest ITILFND_V4 Dumps Valid Version with 428 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments