When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)
A . Request a Change Order from the client for the extra work performed.
B. Document the reviewer’s status and/or comments
C. Review the contract requirements and revise the submittal to comply with these requirements
D. Request a variance from the contract requirements from the client.
E. Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements
Answer: D,E
Latest RCDDv14.1 Dumps Valid Version with 320 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund